Welcome Center remodel August 2019
EXTERIOR:
Remodel SE corner to accommodate wheelchair access with ramp and new entry
ADA access: concrete landing ~ 4' x 4'
concrete or wooden ramp 4' x 30'
concrete or wooden landing 8' x 8'
railing ~80'
(reframe wall for 3' entry door) COMPLETED
install new entry door, trim and finish
Kitchen: remove roof and replace with low slope, insulate
remove roof over kitchen addition 8' x 12'
remove ceiling of same 8' x 12'
remove hip roof over orig kit and reframe upstairs closet
provide for plumbing vent
frame new shed roof 3.5/12, upper walls and ceiling
sheet roof ~14' x 22' and walls ~ 75 sq ft
install metal roofing
cedar shingle new upper walls to match gables ~75 sq ft
install ceiling 8' x 12'
insulate ceiling
remove and frame in entry door
remove? old siding on door wall, install new siding: 1x6 t&g pine 8' x 12'
insulate as necessary
remove back concrete steps and ramp
23 windows
2 picture windows in gallery ~40' x 70"
19 single hung ~24" x 70"
1 picture window in kit ~20" x 36"
1 slider in kitchenette ~36" x 18"
Fill basement openings with treated plywood
Replace broken shingles on N gable end as necessary, remove new vents
remove and replace shingles on E, S and W gables, 120, 100 and 120 sq ft
Repair and replace siding and trim as necessary
SE corner:
( remove concrete steps and entry door) COMPLETED
( frame in door opening) COMPLETED
( install new siding 2 sides SE corner addition) COMPLETED
insulate walls as necessary
New front entry door w/ transom
(Rebuild front porch deck) COMPLETED
(Remove front steps and replace with wood, stained, closed risers) COMPLETED
Prep for paint
Paint - primer plus two topcoats
Stain: front steps, front porch deck, ramp and landing if wood
Face existing chimney w/ composite face brick above roofline
Roof: ~2400 sq ft
tear off, sheet
install designer asphalt shingles, metal on low slope kitchen roof
Install new septic system and sewer line
foundation: sandblast, tuckpoint, mortar drip cap
LANDSCAPING
prep, sprinkler system, sod, etc
fence: 140' x 3' picket
INTERIOR:
Plumbing: 1 water closet, 2 sinks, hot water heater, new water lines, drains and venting for same, exterior water supply
Electrical: new circuits for outlets throughout building, new wiring for lights as necessary
light fixtures throughout
HVAC
electric furnace with new ducting plus heatpump
insulate and isolate upstairs
Gallery
Electrical: new outlets throughout, track lighting
Ceiling: install tin ceiling tiles
Walls: widen doorway for ADA and match existing door and trim
paint walls
paint woodwork
Floor: sand and finish
Entry room - welcome center & Dining room - museum display
Electrical: switched ceiling lights both rooms, 3 way switches
track lighting in dining rm, ceiling fixture in entry
outlets all around
ceiling: tin
walls: remove door to back to make 32" opening
widen entry to kitchen for ADA, match trim
repair plaster after electrical wiring is done and wallpaper
paint painted woodwork
floor: hump in floor? and entry door swing
retain wood floors, repair as necessary, sand, finish
staircase: lightweight trap door to isolate 2nd fl from heating
Kitchen - Museum display
electrical: track lighting, new outlets throughout
replace back half of ceiling to raise and straighten
install tin ceiling
walls: retain bath door and close off permanently
wallpaper, wainscot?
paint woodwork
floor: remove existing, frame out hump, new fir t&g flooring- 200 sq ft
Bathroom
(remove shower and bath fixtures) COMPLETED
(reframe for door, wall off old WC) COMPLETED
install new ADA WC and a sink, install grab bars
sheet vinyl flooring
(wall off chimney) COMPLETED
walls and ceiling - sheet rock and paint, wainscot?
SOUTHEAST CORNER : entry hall, kitchenette on north side, closet on south side
appropriate lighting and electrical outlets
sheet rock and paint walls and ceiling
painted wood trim
install door for closet
install cabinet, countertop and sink
subfloor and commercial vinyl tile flooring
BASEMENT: insulate exterior foundation walls
SECOND FLOOR:
electrical: run new circuits for new outlets and lights
floor: sand and refinish
repair and wallpaper walls
repair and paint ceilings
paint woodwork
EXTERIOR:
Remodel SE corner to accommodate wheelchair access with ramp and new entry
ADA access: concrete landing ~ 4' x 4'
concrete or wooden ramp 4' x 30'
concrete or wooden landing 8' x 8'
railing ~80'
(reframe wall for 3' entry door) COMPLETED
install new entry door, trim and finish
Kitchen: remove roof and replace with low slope, insulate
remove roof over kitchen addition 8' x 12'
remove ceiling of same 8' x 12'
remove hip roof over orig kit and reframe upstairs closet
provide for plumbing vent
frame new shed roof 3.5/12, upper walls and ceiling
sheet roof ~14' x 22' and walls ~ 75 sq ft
install metal roofing
cedar shingle new upper walls to match gables ~75 sq ft
install ceiling 8' x 12'
insulate ceiling
remove and frame in entry door
remove? old siding on door wall, install new siding: 1x6 t&g pine 8' x 12'
insulate as necessary
remove back concrete steps and ramp
23 windows
2 picture windows in gallery ~40' x 70"
19 single hung ~24" x 70"
1 picture window in kit ~20" x 36"
1 slider in kitchenette ~36" x 18"
Fill basement openings with treated plywood
Replace broken shingles on N gable end as necessary, remove new vents
remove and replace shingles on E, S and W gables, 120, 100 and 120 sq ft
Repair and replace siding and trim as necessary
SE corner:
( remove concrete steps and entry door) COMPLETED
( frame in door opening) COMPLETED
( install new siding 2 sides SE corner addition) COMPLETED
insulate walls as necessary
New front entry door w/ transom
(Rebuild front porch deck) COMPLETED
(Remove front steps and replace with wood, stained, closed risers) COMPLETED
Prep for paint
Paint - primer plus two topcoats
Stain: front steps, front porch deck, ramp and landing if wood
Face existing chimney w/ composite face brick above roofline
Roof: ~2400 sq ft
tear off, sheet
install designer asphalt shingles, metal on low slope kitchen roof
Install new septic system and sewer line
foundation: sandblast, tuckpoint, mortar drip cap
LANDSCAPING
prep, sprinkler system, sod, etc
fence: 140' x 3' picket
INTERIOR:
Plumbing: 1 water closet, 2 sinks, hot water heater, new water lines, drains and venting for same, exterior water supply
Electrical: new circuits for outlets throughout building, new wiring for lights as necessary
light fixtures throughout
HVAC
electric furnace with new ducting plus heatpump
insulate and isolate upstairs
Gallery
Electrical: new outlets throughout, track lighting
Ceiling: install tin ceiling tiles
Walls: widen doorway for ADA and match existing door and trim
paint walls
paint woodwork
Floor: sand and finish
Entry room - welcome center & Dining room - museum display
Electrical: switched ceiling lights both rooms, 3 way switches
track lighting in dining rm, ceiling fixture in entry
outlets all around
ceiling: tin
walls: remove door to back to make 32" opening
widen entry to kitchen for ADA, match trim
repair plaster after electrical wiring is done and wallpaper
paint painted woodwork
floor: hump in floor? and entry door swing
retain wood floors, repair as necessary, sand, finish
staircase: lightweight trap door to isolate 2nd fl from heating
Kitchen - Museum display
electrical: track lighting, new outlets throughout
replace back half of ceiling to raise and straighten
install tin ceiling
walls: retain bath door and close off permanently
wallpaper, wainscot?
paint woodwork
floor: remove existing, frame out hump, new fir t&g flooring- 200 sq ft
Bathroom
(remove shower and bath fixtures) COMPLETED
(reframe for door, wall off old WC) COMPLETED
install new ADA WC and a sink, install grab bars
sheet vinyl flooring
(wall off chimney) COMPLETED
walls and ceiling - sheet rock and paint, wainscot?
SOUTHEAST CORNER : entry hall, kitchenette on north side, closet on south side
appropriate lighting and electrical outlets
sheet rock and paint walls and ceiling
painted wood trim
install door for closet
install cabinet, countertop and sink
subfloor and commercial vinyl tile flooring
BASEMENT: insulate exterior foundation walls
SECOND FLOOR:
electrical: run new circuits for new outlets and lights
floor: sand and refinish
repair and wallpaper walls
repair and paint ceilings
paint woodwork
proposed plan
welcome center room with 100+ year old desk from Kendrick store
new entry and bath
existing roof line
proposed with 3.5/12 pitch